Project name Investor Name and TIN number Brief description of the project The amount of investments, thousand RUB Number of jobs Region Branch Treaty (number, date, expiry date)
Construction of a four-section residential building on Krasnoarmeyskaya str., Yalta Rekon-Krym-Stroy LLC, 9102172238 Construction of a four-section residential building on Krasnoarmeyskaya str., Yalta, on the land plot of approximate area 0.7131 ha 800000 0
24, 13/07/2015, 31/12/2025
Краткое описание
Construction of a four-section residential building on Krasnoarmeyskaya str., Yalta, on the land plot of approximate area 0.7131 ha
Construction of a modern garment factory Simferopol Garment Factory Arden LLC, 9102016091 Construction of a modern garment factory on the land plot of 0.3 ha located near the Yalta-Yevpatoria bypass road 10250 0
21, 15/06/2015, 31/12/2064
Краткое описание
Construction of a modern garment factory on the land plot of 0.3 ha located near the Yalta-Yevpatoria bypass road
Arrangement of the fishery to supply fresh and processed fish products to the consumer market Stavnik LLC, 9110008270 Arrangement of the fishery to supply fresh and processed fish products to the consumer market on the land plots of approximate total area 2.2 ha located in the territory of Olenevskoe village settlement of the Chernomorsky District of the Republic of Crimea 8000 0
19, 15/06/2015, 31/12/2040
Краткое описание
Arrangement of the fishery to supply fresh and processed fish products to the consumer market on the land plots of approximate total area 2.2 ha located in the territory of Olenevskoe village settlement of the Chernomorsky District of the Republic of Crimea
Arrangement of the in-shore fisheries to ensure the year-round supply of fish products to the consumer market Staraya Pristan LLC, 9110011033 Arrangement of the in-shore fisheries to ensure the year-round supply of fish products to the consumer market on the land plots of approximate total area 1.8 ha located in the territory of Olenevskoe village settlement of the Chernomorsky District of the Republic of Crimea 8000 0
18, 15/06/2015, 31/12/2040
Краткое описание
Arrangement of the in-shore fisheries to ensure the year-round supply of fish products to the consumer market on the land plots of approximate total area 1.8 ha located in the territory of Olenevskoe village settlement of the Chernomorsky District of the Republic of Crimea
Development of the grape-growing industry near Opolznevoe settlement Horizon-service LLC , 9103069850 Development of the grape-growing industry near Opolznevoe settlement on the land plot of approximate area 12.32 ha located outside the territory of Opolznevoe village settlement of the Yalta City District Municipality of the Republic of Crimea 20968 0
17, 15/06/2015, 31/12/2033
Краткое описание
Development of the grape-growing industry near Opolznevoe settlement on the land plot of approximate area 12.32 ha located outside the territory of Opolznevoe village settlement of the Yalta City District Municipality of the Republic of Crimea
Reconstruction of Simferopol CHPP with generating capacity improvement by 230 MW Krymteploelektrotsentral JSC, 9102070194 Reconstruction of six gas turbine plants of nominal electric capacity 32 MT each; six waste-heat boilers and three steam turbines of total capacity 60 MW 16184400 0
07, 10/04/2015, 31/12/2030
Краткое описание
Reconstruction of six gas turbine plants of nominal electric capacity 32 MT each; six waste-heat boilers and three steam turbines of total capacity 60 MW
Reconstruction of Saky Central Heating Systems CHPP with generating capacity improvement by 84 MW Krymteploelektrotsentral JSC , 9102070194 Reconstruction of: two gas turbine plants of nominal electric capacity 32 MT each; two waste-heat boilers and a steam turbine of total capacity 20 MW 6102800 0
06, 10/04/2015, 31/12/2030
Краткое описание
Reconstruction of: two gas turbine plants of nominal electric capacity 32 MT each; two waste-heat boilers and a steam turbine of total capacity 20 MW
Cement plant, concrete production Gen invest LLC, 9102171957 Construction of a modern dry mix process plant with a full production cycle, output capacity 30,000 t/month Acquisition and installation of a grinding plant of capacity 80,000 t/months (outgoing clinker processing) 939195 0
05, 31/03/2015, 31/12/2016
Краткое описание
Construction of a modern dry mix process plant with a full production cycle, output capacity 30,000 t/month Acquisition and installation of a grinding plant of capacity 80,000 t/months (outgoing clinker processing)
Development of the winemaking on the basis of the assets of the Republic of Crimea in Koktebel urban-type settlement Krymskaya loza LLC, 9108003300 Recovery of a production complex in Koktebel urban-type settlement and bringing it to the level of a modern highly productive plant producing Koktebel wines and wine materials, including by restoring the vineyards 1165240 0
04, 20/03/2015, 31/12/2064
Краткое описание
Recovery of a production complex in Koktebel urban-type settlement and bringing it to the level of a modern highly productive plant producing Koktebel wines and wine materials, including by restoring the vineyards